US 51 Corridor Study (Stoughton-McFarland) - Maps

Project location

US 51, I-39/90 (east of Stoughton) to US 12/18 (Beltline) north of McFarland, in Dane County.

Map key - Thick orange line is the project overview/location. Green line is project alternative corridor. Blue tear drop with dot in center is the project boundary.
View SW, US 51 Corridor Study, I-39/90 (Stoughton) to US 12/18 (McFarland) in a larger map.

Oct. 15, 2012 - PIM

View all maps/exhibits from this meeting (29.2 MB) OR view individual files below AND on the Public involvement pg.

Crash summary 2007-2009

  • US 51 segments and County B
  • US 51 intersections

Alternatives

Traffic volumes/operations

The analysis of existing and future operating characteristics of a roadway can be measured using Level of Service (LOS) to provide an indication of the ability of the roadway to satisfy both existing and future travel demand.

LOS is a quantitative measure of the quality of service of a transportation facility. The LOS measure is broken down into six letter grades, A through F with A being the best and F being the worst. LOS measure of D/E is considered the lowest acceptable rating for an intersection.

Questions about the content of this page:
WisDOT Southwest Region Office-Madison, swr.dtsd@dot.wi.gov
Last modified: June 27, 2013

All external hyperlinks are provided for your information and for the benefit of the general public. The Wisconsin Department of Transportation does not testify to, sponsor or endorse the accuracy of the information provided on externally linked pages. Some pages contain links to other documents and media types (PDF, Word, Flash, Video, etc.) and require free plugins to work. Visit our software information page for assistance.