WIS 15 (US 45-Lily of the Valley Dr.) Expansion - Schedule

An intersection on WIS 15.

For more information on Public Information Meetings (PIM), hearings and other public activities, visit Public involvement.

Current (this year)

  • 2014
    • Design work
    • Real estate acquisition scheduled to start

Future (next year and beyond)

  • 2015 - Real estate acquisition to continue
  • 2017-late 2018 - Utility relocation anticipated
  • Late 2018 - Construction scheduled to start


Past (anything prior to today)

2013


2012


2010

  • Oct. 2010 - WIS 15 enumerated by Transportation Projects Commission (TPC)

2009

  • Study completed
  • Dec. 28, 2009 - Final Environmental Impact Statement (FEIS) approved by Federal Highway Administration (FHWA)
  • Summer 2009 - Preliminary (30 percent) design plans complete
  • Feb. 2, 2009 - PIM

2007

  • Jun. 2007 - Preferred alternative and corridor selected
  • Jun. 2007 WisDOT announces selection of Alternative 3, bypassing Hortonville to the north
  • Feb. 2007 - Public Hearing and open comment period for Draft EIS (DEIS)

2006

  • Dec. 2006 - DEIS approved by FHWA
  • Jan. 2006 - DEIS submitted to FHWA

2005

  • Data collection completed and impacts to environment are qualified
  • Winter 2005 - Newsletter published and PIM with project update

2004

  • Fall 2004 - Agency approval of alternatives to be studied in DEIS received
  • Summer 2004 - Alternatives modified and resubmitted to regulatory agencies while data collected for alternatives

2003

  • Winter 2003-2004 - Data collected for each alternative is analyzed. Alternatives carried forward to study are presented to regulatory agencies
  • Summer 2003 - Value Engineering Study completed and additional alternatives brought forward and shown in Aug. 2003 newsletter
  • Spring-summer 2003 - Alternatives to be studied in EIS presented. Info. gathering started to evaluate cost and impacts of alternatives
  • Spring 2003 - PIM

2002

  • Winter 2002-2003 - WIS 15 alternatives developed with cooperation of Advisory Committee (AC) and presented to cooperating agencies
  • Aug. 2002 - Second WIS 15 corridor plan completed, Greenville to US 41

2001

  • Feb. 2001 - WIS 15 corridor plan completed, US 45 to Lily of the Valley Dr.

Questions about the content of this page:
WisDOT Northeast Region Office, ner.dtsd@dot.wi.gov SSI - Contacts
Last modified: Mar. 6, 2014

All external hyperlinks are provided for your information and for the benefit of the general public. The Wisconsin Department of Transportation does not testify to, sponsor or endorse the accuracy of the information provided on externally linked pages. Some pages contain links to other documents and media types (PDF, Word, Flash, Video, etc.) and require free plugins to work. Visit our software information page for assistance.