WIS 15 expansion study - schedule

Date Type of work/activity
December 2006 Draft Environmental Impact Statement (DEIS) is submitted to the Federal Highway Administration (FHWA) for approval.
February 2007 Public hearing and open comment period held for DEIS.
June 2007 Corridor is selected.
February 2, 2009 Public information meeting (PIM).
Summer 2009 Preliminary (30%) design plans complete.
Winter 2009/2010 Final Environmental Impact Statement (FEIS) approval.
Fall 2010 Public hearing for official mapping.
2010 or later WIS 15 competes for major funding for construction versus other projects statewide every even-numbered year.

Photo of vehicles driving on WIS 15.

 


Drivers & Vehicles | Safety | Travel | Plans & Projects | State Patrol | Doing Business | Programs for Local Gov't

Air | Bicycles | Bus/transit | Cars | Motorcycles | Pedestrian | Rail | Trucks | Waterways

Home | News | About Us | Research & Library | A-Z Index